NexusDelivery governance
← ACME Sports Migration · Email drafts

Tech-lead onboarding

Generated live by the Node port. This is the actual HTML Nexus would send.

Nexus · Delivery Methodology & Gated Process
Welcome to ACME Sports Migration
Your Gate 0 checklist & what to expect

Hi Charly,

My name is Nexus, and I'll be your delivery methodology and gated process partner for ACME Sports Migration. Think of me as your behind-the-scenes accountability system — I help keep the project on track, flag risks early, and make sure nothing falls through the cracks.

SOW Governance Briefing
SOW: 982714 - GC Migration and CX Transformation
Complexity: High Complexity Migration Program
Project scope
  • Migrate Customer from legacy platform to Genesys Cloud CX (GCCX) for 2000 agents
  • Approximate 10-month duration with 6 go-live events aligned to Customer's pre-defined LOBs
  • Project Initiation including kick-off, communication plan, PM assignment, and Technical Lead capped at 340 hours
  • Discovery & Design: up to 20 sessions of up to 4 hours each
  • FRS deliverables with up to 2 review cycles
  • Genesys Cloud System Configuration: base config, Voice Services (BYOC Cloud), Call/Email/Web Messaging routing, integrations and API consulting
  • Voice: up to 2 Sites, 5 Locations, 4 Trunks, 300 User DIDs
  • Up to 24 Schedules
  • Up to 200 ancillary call flows
  • Up to 100 Queues
  • Up to 100 Scripts
  • Up to 2 recording retention policies
  • Email Routing (Use Case CE16): up to 10 email addresses, 1 domain, up to 100 Email Queues, up to 100 Email Flows
  • Web Messaging Routing (Use Case CE34): up to 4 API consult sessions, up to 2 Web Message Flows and 2 Queues
  • Integrations: SSO (SAML), up to 2 AppFoundry apps (Audiohook, Verint Connector for QM), up to 3 OAuths for Verint WFM, Web Service Data Actions, API consulting for Embeddable Framework
  • System Testing: Genesys QA, Smoke Testing (up to 6 rounds, up to 500 concurrent test ports), and UAT support (up to 8 hrs/day for 30 business days)
  • Development System configuration with one-time code replication from Prod Org to Dev Org
  • Go Live: planning sessions, Go-Live support (up to 8 hrs/day for 30 business days), and up to 2 TOI/knowledge transfer sessions
  • DevOps: CX as Code QuickStart and CX as Code Consulting (remote, up to 80 hours over four weeks)
  • Value Realization Program with four workstreams and defined deliverables
  • Fixed-price total $875,000.00 USD with milestone-based billing
Risks
  • Discovery is iterative and may require a Project Change Request (PCR) with potential additional funding
  • Customer currently has a large number of call flows built from 5 templates and over 700 Email flows
  • Scope caps flows at 100 each with intent to consolidate — additional flows require Customer configuration or a Change Order
  • Configuration work cannot start until Customer provides FRS acceptance/sign-off
  • Up to 2 FRS review cycles included
  • If Discovery and Design goes beyond two weeks after project start, the entire project schedule may be impacted/delayed and require a Change Order
  • Go-Live planning and support assumptions are inconsistent in the artifact (some sections reference one go-live event while objectives/notes reference six go-live events)
  • Customer responsible for UAT design and execution
  • UAT-driven design changes require QA and UAT retest and fall outside estimated hours
  • Customer responsible for all development on back-end systems and for third-party system costs, effort, and integration
  • Genesys not responsible for issues arising from third-party applications or Customer network configurations
  • Staffing may require 2 to 6 weeks' notice after signed SOW and supporting Purchase Order
  • On-site resource requests trigger additional time and travel costs via PCR or separate SOW
  • Travel and expenses not included in price
  • Customer responsible for data privacy/regulatory compliance (GDPR, CCPA, etc.)
  • Recording not allowed for CX as Code QuickStart presentation
  • Milestone acceptance depends on mutually agreed Definition of Done and VP sign-off within defined Acceptance Periods
  • Non-acceptance after repeated attempts allows Customer to terminate without penalty
Margin protection areas
  • Flow consolidation risk: Customer has large existing voice flow set and 700+ email flows but scope caps flows at 100 each — manage consolidation expectations to avoid uncompensated overflow
  • Technical Lead effort capped at 340 hours (100 call flow redesign, 40 queues, 200 tech lead) — track burn against cap
  • Discovery limited to 20 sessions of up to 4 hours; scope growth must route through PCR
  • FRS sign-off gates all configuration work; delays in Customer sign-off can stall billing and schedule
  • Two-week Discovery & Design timeline constraint before schedule impact triggers Change Order
  • Go-live event count ambiguity (one vs. six) directly affects Go-Live support effort and cost
  • UAT and Go-Live support fixed at up to 8 hrs/day for 30 business days each — additional demand requires change control
  • Code promotion Prod-to-Dev is one-time only; additional promotions require Change Order
  • On-site requests, additional API/consulting sessions, and additional test rounds require PCR or separate SOW
  • Customer-owned dependencies: CSV user data, identity provider certificates, working test data, RESTful third-party interfaces, back-end web services meeting data action requirements
  • Travel and expenses excluded from fixed price and billed separately — ensure approvals before incurring
  • AppFoundry integration assistance capped at 3 hours; vendor-side config and defect remediation excluded
  • Special Partnership Incentive reduces subtotal by $170,000.00 USD, tightening margin against the $1,045,000.00 USD baseline scope
Gate 0 actions
  • Confirm assigned Genesys Project Manager and Technical Lead and validate the 340-hour Technical Lead cap against expected scope
  • Validate the go-live model discrepancy in the artifact (one vs. six go-live events) and align Go-Live support assumptions before commitments
  • Secure Customer's named Project Manager and single point of contact per Customer Responsibilities
  • Confirm required Purchase Order is in place and account for the 2-to-6-week staffing notice window
  • Establish FRS sign-off process and Acceptance Period expectations with the Customer VP owning the project
  • Baseline the existing call flow and 700+ email flow inventory to plan consolidation against the 100-flow caps
  • Confirm Customer readiness to provide CSV user data, IdP certificates/config, RESTful interfaces, and working test data
  • Set up governance per Appendix B (Executive Governance, Design Authority/Change Boards, SCRUMs, stand-ups)
  • Establish Definition of Done and milestone acceptance criteria aligned to the payment milestones
Executive tech lead focus
  • Drive Discovery & Design within the 20-session/two-week constraint and produce a defensible FRS and Critical Risks & Dependencies list
  • Lead flow consolidation strategy across voice and email to fit within the 100-flow scope caps and document overflow as change control
  • Plan Genesys Cloud base configuration, Voice Services (BYOC Cloud), and routing (call, email, web messaging) using predefined use cases (CE16, CE34)
  • Coordinate integrations delivery: SSO (SAML), AppFoundry apps (Audiohook, Verint QM), Verint WFM OAuths, and Web Service Data Actions
  • Define QA, Smoke Testing (up to 6 rounds, 500 concurrent ports), and UAT support approach with clear Customer responsibilities
  • Establish CX as Code / CI/CD DevOps approach and confirm Customer DevOps prerequisites and pipeline ownership
  • Align Value Realization Program workstreams and deliverables with the initial Go-Live business group
  • Manage the one-time Prod-to-Dev code replication and production readiness prior to each go-live
Your Checklist

Fill it out right in this email, then hit Reply and send it back to me:

  • Type x inside the brackets to mark an item complete: [x]
  • Type x in the N/A field if an item does not apply: N/A: [x]
  • Type your explanation after Notes: if a deliverable could not be met
Core
[ ] G0-01 | Delivery Manager Assigned if applicable N/A: [ ] Notes:
[ ] G0-02 | Deal Review (DAP Tab 1&2) N/A: [ ] Notes:
[ ] G0-03 | Complexity Evaluation N/A: [ ] Notes:
SS&AI
[ ] G0-SSAI-01 | IVR estimates provided by SS&AI Presales Architects N/A: [ ] Notes:
[ ] G0-SSAI-02 | Enhanced TTS bundle sold in SO for Polly voice N/A: [ ] Notes:
[ ] G0-SSAI-03 | Virtual Agent sold for alphanumeric, address, name, email address, drug names, FAQs etc. N/A: [ ] Notes:
[ ] G0-SSAI-04 | SS&AI Reusable Assets Leveraged? N/A: [ ] Notes:
Reporting
[ ] G0-RPT-01 | Validate customer reporting goals, collect example requirements, and success criteria N/A: [ ] Notes:
[ ] G0-RPT-02 | Assess data sources: 1) Standard Reports 2) A3S, Liquid App, or App Foundry Partner 3) A3S, Liquid App, or App Foundry Partner N/A: [ ] Notes:
[ ] G0-RPT-03 | Customer Data Integration: GC Lakehouse, APIs, or EventBridge N/A: [ ] Notes:
[ ] G0-RPT-04 | Based on chosen data sources, ensure customer requirements can be achieved, if not, data source re-evaluation is required N/A: [ ] Notes:
[ ] G0-RPT-05 | Identify gaps and opportunities between out-of-the-box reporting and collected business needs. N/A: [ ] Notes:
[ ] G0-RPT-06 | Define high-level solution approach and architecture N/A: [ ] Notes:
[ ] G0-RPT-07 | Estimate effort, timeline, and dependencies for SOW N/A: [ ] Notes:
What to Expect From Me
  • Every Friday at 8am your time, I'll send you a project status email
  • When you submit an update mid-week, I'll confirm receipt and log your progress immediately
  • Gate work can run in parallel when approved by delivery leadership
Who Is Looped In
Charly Yi - unknown@example.com
-
Nexus
Delivery Methodology & Gated Process Director
nexus@nexus-genesys.com