Gate 0: Pre-Sales and Kickoff Preparation   Needs Review

14 in-scope items from checklist JSON; 14 on project record.

Core

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G0-01 Delivery Manager Assigned if applicable Complete from_reply Morgan Lee assigned as DM for Contoso. OK
G0-02 Deal Review (DAP Tab 1&2) Not started DAP Tab 1 complete; Tab 2 review scheduled 5/28 with sales. OK
G0-03 Complexity Evaluation Not started OK

Reporting

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G0-RPT-01 Validate customer reporting goals, collect example requirements, and success criteria Not started Workshop notes in Confluence; customer samples pending. OK
G0-RPT-02 Assess data sources: 1) Standard Reports 2) A3S, Liquid App, or App Foundry Partner 3) A3S… Needs Review Leaning Standard Reports + Lakehouse; items 2 and 3 in checklist are duplicate wording (Needs Review). NEEDS REVIEW
G0-RPT-03 Customer Data Integration: GC Lakehouse, APIs, or EventBridge Not started OK
G0-RPT-04 Based on chosen data sources, ensure customer requirements can be achieved, if not, data s… Not started OK
G0-RPT-05 Identify gaps and opportunities between out-of-the-box reporting and collected business ne… Not started OK
G0-RPT-06 Define high-level solution approach and architecture Not started OK
G0-RPT-07 Estimate effort, timeline, and dependencies for SOW Not started OK

SS&AI

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G0-SSAI-01 IVR estimates provided by SS&AI Presales Architects Complete from_reply Estimates attached in deal folder. OK
G0-SSAI-02 Enhanced TTS bundle sold in SO for Polly voice Not started Confirming with sales on SO line item. OK
G0-SSAI-03 Virtual Agent sold for alphanumeric, address, name, email address, drug names, FAQs etc. Not started OK
G0-SSAI-04 SS&AI Reusable Assets Leveraged? Not started OK

Gate 1: Transition and Kickoff Preparation   Needs Review

24 in-scope items from checklist JSON; 24 on project record.

Core

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G1-01 Pre-Sales to Delivery transition; review Pre-DAP Complete from_reply Kickoff transition call held 5/22; Pre-DAP shared with delivery. OK
G1-02 SoW Review Not started OK
G1-03 Set up Design Review Sessions with SS&AI, WFM, Reporting teams Not started OK
G1-04 SO Review Not started OK
G1-05 Define/Plan Train-the-Trainer, Knowledge Transfer Not started OK
G1-06 Verify Org is spun-up Not started OK
G1-07 Pre-Mortem Exercise [WIP] Needs Review NEEDS REVIEW
G1-08 Discovery Agenda and Questions Not started OK
G1-09 Internal agreement on Technical Documentation; Prepped and groomed FRS Not started OK

Reporting

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G1-RPT-01 Conduct internal handoff from sales to delivery team (scope, assumptions). Not started OK
G1-RPT-02 Confirm stakeholders, roles, and communication cadence Not started OK
G1-RPT-03 Review scope, timeline, and deliverables with the customer Not started OK
G1-RPT-04 Validate access, permissions, and environments (Customer access needs, FedRamp, Partner Ac… Not started OK
G1-RPT-05 Finalize project plan and milestones Not started OK

SS&AI

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G1-SSAI-01 Review SS&AI Estimates Not started OK
G1-SSAI-02 Align on SS&AI scope, NA/COE resource split, ramp date and timeline commitments, if any Not started OK
G1-SSAI-03 Create staffing plan or collaborate with SS&AI Delivery Manager, if assigned to create a s… Not started OK
G1-SSAI-04 Allocate SS&AI Designer and SS&AI Dev Lead Not started OK
G1-SSAI-05 Check if customer has enhanced TTS bundle for Polly voice. Otherwise, set customer expecta… Not started OK
G1-SSAI-06 Set customer responsibilities on multi lingual translations Not started OK
G1-SSAI-07 Share call flows, intent guide and API documentation from presales with the allocated SMEs Not started OK
G1-SSAI-08 Identify customer POCs for design reviews and approvals, API specs & development Not started OK
G1-SSAI-09 If third party bot platforms such as Dialog Flow is in scope, ask customer to provide acce… Not started OK
G1-SSAI-10 If virtual agents, discuss use cases that Sales proposed to customer and PCI compliance Not started OK

Gate 2: Discovery and Design   Not started

54 in-scope items from checklist JSON; 1 on project record.

Core

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G2-00 What is existing and project success criteria for Recognition and Containment for NLU Not started OK
G2-01 Continue Design Review Sessions with SS&AI, WFM, Reporting teams Not started OK
G2-02 Gain Access to Customer ORG via AuthOrgs Not started OK
G2-03 Review Routing design with WFM Resrouce to ensure WFM would not be impacted by design. Not started OK
G2-04 Customer API Review Not started OK
G2-05 Review the customer's API and see if they meet best practices. API that do not meet our re… Not started OK
G2-05a Consult with the customer to update their API to follow best practices to be more efficien… Not started OK
G2-05b Review the API and see if a PCR is required to make the existing API work with Genesys Clo… Not started OK
G2-06 The API best practices can be found under the following LINK Not started OK
G2-07 Complete API Questionnaire Not started OK
G2-08 Decision regarding ORF, CE43, or custom routing build Not started OK
G2-09 Network Advisory Not started OK
G2-10 Conduct the Network Advisory session Not started OK
G2-11 If purchased, conduct the Audio Quality Assessment (AQA) Not started OK
G2-12 Is the customer using WebRTC phones? If yes, have they run a WebRTC diagnostic from each l… Not started OK
G2-13 Populated FRS Not started 2026-07-10 Pilot-only due date on project record for escalation demo; not asserted as xlsx column value (D-P1-11). OK
G2-14 Ensure naming conventions are standardised. Note: See the Naming Standardization tab in th… Not started OK
G2-15 Call Flow Documented in Whiteboard/Lucid/Visio? Not started OK
G2-16 Architect: Error Handling. What action to take when a flow error occurs. Disconnect, Trans… Not started OK
G2-17 BYOC SIP Trunk Questionnaire Not started OK
G2-18 HIPPA/PCI Customer Acknowledgement Not started OK
G2-19 Complete Discovery Workshop Questionnaires Not started OK
G2-20 Review SS&AI Section if SS&A Team is engaged on the project Not started OK
G2-21 Complete Call Flow design and associated Data Table designs. See the FRS for design docume… Not started OK
G2-22 911 / E-911 (GCloud Voice, BYOC, AppFoundry (Intradeo, etc)) Not started OK
G2-23 Check if any locations are in India or other regions with Legal requirements Not started OK

Reporting

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G2-RPT-01 Gather detailed reporting requirements, use cases, and customer provided examples Not started OK
G2-RPT-02 Customer data source build, provide hands on access guidance, BYO kick-off assets, and kno… Not started OK
G2-RPT-03 Ensure the proper Participant Attributes (CCA's), External Tags, Milestones, and Outcomes … Not started OK
G2-RPT-04 Define KPIs, metrics definitions, and data sources Not started OK
G2-RPT-05 Review data availability, retention, and freshness expectations Not started OK
G2-RPT-06 Discuss reporting architecture, data model, joins required Not started OK
G2-RPT-07 Produce design artifacts (data dictionary, report mockups, data model) Not started OK

SS&AI

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G2-SSAI-01 Polly voice selection - share demo link Not started OK
G2-SSAI-02 What is existing and project success criteria for Recognition and Containment for NLU Not started OK
G2-SSAI-03 Review presales artifacts - call flows, intent guide, API specs, etc. and confirm with the… Not started OK
G2-SSAI-04 Check for use cases such as alphanumeric, address, name capture etc. that require Virtual … Not started OK
G2-SSAI-05 Leverage SS&AI resuable assets wherever possible Not started OK
G2-SSAI-06 Schedule design workshops and set regular cadence to accomplish target design completion m… Not started OK
G2-SSAI-07 Fill out API tracking sheet and use it to drive API status, target dates etc. Not started OK
G2-SSAI-08 SS&AI Dev Lead to draft TDS for each Whiteboard Not started OK
G2-SSAI-09 Architect: Error Handling. What action to take when a flow error occurs. Disconnect, Trans… Not started OK
G2-SSAI-10 Design Checkpoint between Core and SS&AI. (SS&AI Designer, SS&AI Dev Lead, Core Tech Lead)… Not started OK
G2-SSAI-11 Update Whiteboard and/or TDS with Milestones, Outcomes, & Participant Data. SS&AI Dev lea… Not started OK
G2-SSAI-12 Adhere to SS&AI reporting standards and review them with customer. Not started OK
G2-SSAI-13 If customer is migrating from Nuance - solution gaps such as custom grammar, if necessary … Not started OK
G2-SSAI-14 If Visual IVR is in scope, collaborate with Digital SME on the list of attributes returned… Not started OK
G2-SSAI-15 If third party bot platforms such as Dialog Flow is in scope, work with customer to config… Not started OK
G2-SSAI-16 Discuss and document PII, PHI or PCI handling in secure flows Not started OK
G2-SSAI-17 Collaborate with Architect on API and TTS rate limit sizing Not started OK
G2-SSAI-18 Add transitional prompts between back-to-back API calls. Not started OK
G2-SSAI-19 Seek design sign-off on Whiteboards & TDS and archive email approvals Not started OK
G2-SSAI-20 Schedule design walkthrough with developers upon design sign-off Not started OK
G2-SSAI-21 Considerations for bots and virtual agents usage & cost for a single call Not started OK

Gate 3: Build and Configuration   Not started

47 in-scope items from checklist JSON; 0 on project record.

Core

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G3-01 Continue Design Review Sessions with SS&AI, WFM, Reporting teams Not started OK
G3-02 Completed FRS approved by customer Not started OK
G3-03 Completed flow designs approved by customer Not started OK
G3-04 Conduct Status updates with PM Not started OK
G3-05 Test Data is provided by the customer for QA Not started OK
G3-06 Engage QA to start their tasks Not started OK
G3-07 Review Edge Sizing best practices based on CPU Not started OK
G3-08 Link to Edge Sizing Calculator Not started OK
G3-09 Conduct Limits review and submit requests for increases. Note: You can use Pythons script… Not started OK
G3-10 Schedule the Smoke Test Not started OK
G3-11 Verify the Media Sites on BYOC trunks. The media regions set on this site are used for inb… Not started OK
G3-12 Enable Sensitive Data Masking if needed. Not started OK
G3-13 Ensure naming conventions are standardised in the build Not started OK
G3-14 Architect: Error Handling Not started OK
G3-15 Architect: 10K executed steps per flow limit (Check inqueue for how long a call can queue … Not started OK
G3-16 Architect: Use NOT_SET Not started OK
G3-17 Architect: Remove audio warning messages by using the expression 'ToAudioTTS(NOT_SET)' and… Not started OK
G3-18 Architect: Use ToAudio(FindUserPrompt("")) for audio playback steps so flows do not have t… Not started OK
G3-19 Architect: Disable Listen for Extension Dialing unless required. Not started OK
G3-20 Architect: Disable Speech Recognition unless it is required for Architect Menus. All Speec… Not started OK
G3-21 Architect: Audio barge-in. Note: Make sure legal/compliance disclaimers cannot be interupt… Not started OK
G3-22 Architect: Remove unused variables Not started OK
G3-23 Architect: Remove Debug Code Not started OK
G3-24 Architect: Initialized Variables Variable initial values should be set under the Data Reso… Not started OK
G3-25 Architect: Proper Use of Flow.Variables and Task.Variables Task.Variables will release mem… Not started OK
G3-26 Architect: HIPPA/PCI PII check Make sure any HIPPA/PCI PII is collected in secure flows. Not started OK
G3-27 Architect: Review flow size. If flow exceeds 60% of max size then serious consideration s… Not started OK
G3-28 Other Best Practices Not started OK

Reporting

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G3-RPT-01 Create data views, journey flows, transformations, and curated datasets Not started OK
G3-RPT-02 Ensure the proper Participant Attributes (CCA's), External Tags, Milestones, and Outcomes … Not started OK
G3-RPT-03 Develop reports and dashboards (standard or custom BI tools) Not started OK
G3-RPT-04 Implement filters, calculations, and performance optimizations Not started OK
G3-RPT-05 Validate data accuracy against Genesys Cloud source metrics Not started OK
G3-RPT-06 Iterate based on customer feedback Not started OK

SS&AI

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G3-SSAI-01 Train the bot and conduct speech science review, if Speech Scientist was not engaged in de… Not started OK
G3-SSAI-02 Think through bot usage prior to build - use bot flows for speech recognition only, minimi… Not started OK
G3-SSAI-03 To minimize API latency, fill perceived caller silence with percolation sound and execute … Not started OK
G3-SSAI-04 Data passthrough alignment between Flows Not started OK
G3-SSAI-05 HIPPA/PCI Treatment for Secure Flows Not started OK
G3-SSAI-06 Maintain dev tracker to report % complete for NLU & self-service modules Not started OK
G3-SSAI-07 Submit test data request for unit testing Not started OK
G3-SSAI-08 Discuss test data validity and refresh process with customer Not started OK
G3-SSAI-09 Conduct handoff to QA Not started OK
G3-SSAI-10 Collaborate with QA lead for demos Not started OK
G3-SSAI-11 Test API endpoints to see if they match the approved specs. Report API defects, if any Not started OK
G3-SSAI-12 Update SS&AI Bot Register Not started OK
G3-SSAI-13 Configure flow outcomes and milestones to identify false accepts and misrecognitions. Trac… Not started OK

Gate 4: Post-Build QA and UAT   Not started

22 in-scope items from checklist JSON; 0 on project record.

Core

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G4-01 Continue Design Review Sessions with SS&AI, WFM, Reporting teams Not started OK
G4-02 Was SIT Testing completed Not started OK
G4-03 Plan and conduct training sessions Not started OK
G4-04 New Features and Deprecations Not started OK
G4-05 Was QA Engaged? Not started OK
G4-06 Create Technical Design Specifications and Architectural Diagrams for Customizations Requi… Not started OK
G4-07 Pre-mortem project management strategy Not started OK
G4-08 Modify Training Materials to Match Customer Functionality for Trainer the Trainer Not started OK
G4-09 Verify Documentation Not started OK
G4-10 Verify Edge Count and Sizing is complete Not started OK
G4-11 Verify Limit Increases are complete Not started OK
G4-12 Conduct the Smoke Test Not started OK
G4-13 Review the training plan Not started OK

Reporting

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G4-RPT-01 Perform QA and reconciliation of metrics Not started OK
G4-RPT-02 Optimize queries, refresh schedules, and performance Not started OK
G4-RPT-03 Prepare documentation (data definitions, report usage guides) Not started OK
G4-RPT-04 Conduct knowledge transfer and enablement sessions Not started OK
G4-RPT-05 Finalize support and handoff plan Not started OK

SS&AI

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G4-SSAI-01 Monitor API performance, TTS license usage during load tests Not started OK
G4-SSAI-02 Establish SLAs for UAT defects based on priority & severity and minimum information needed… Not started OK
G4-SSAI-03 Code migration planning & remediation of errors from Terraform extract Not started OK
G4-SSAI-04 Archive exports of data tables, data actions, prompt list and flows on SharePoint Not started OK

Gate 5: Go-Live   Not started

21 in-scope items from checklist JSON; 0 on project record.

Core

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G5-01 Continue Design Review Sessions with SS&AI, WFM, Reporting teams Not started OK
G5-02 Completed FRS uploaded to Project Not started OK
G5-03 Completed TDS uploaded to Project Not started OK
G5-04 Completed Call Flows uploaded to Project Not started OK
G5-05 Review Smoke Testing Results Not started OK
G5-06 Verify Edge Deployment Not started OK
G5-07 Feature Deprecation final review Not started OK
G5-08 Validate customer Care onboarding Not started OK
G5-09 Validate customer Auth Org setup Not started OK
G5-10 Create the Go Live Checklist Not started OK
G5-11 Confirm Customer training is complete Not started OK

Reporting

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G5-RPT-01 Validate production access Not started OK
G5-RPT-02 Confirm data freshness monitoring and alerting Not started OK
G5-RPT-03 Complete user acceptance testing (UAT) sign-off Not started OK
G5-RPT-04 Deliver final reports/dashboards to business users Not started OK
G5-RPT-05 Establish post-go-live support and success metrics Not started OK

SS&AI

Item IDTaskStatusN/ADue dateCompletion dateNotesReview
G5-SSAI-01 Validate production API endpoints prior to go live Not started OK
G5-SSAI-02 Ensure all production flags and data tables are configured and any test harness or menus a… Not started OK
G5-SSAI-03 Proactive monitoring of NLU & self-service metrics. E.g. proactive updates to training phr… Not started OK
G5-SSAI-04 Establish rollback plan for IVR Not started OK
G5-SSAI-05 Conduct post launch bot performance review to analyze and report on system performance and… Not started OK